Gantt charts display a project schedule or show changes in activity over time?

48. Gantt charts display a project schedule or show changes in activity over time?

  1. True
  2. False

Answer: A) True

Explanation:

Gantt charts are used to indicate variations in activity over time or to display a project timeline. A Gantt chart depicts the actions that must be accomplished before others can begin, as well as the distribution of resources.