How many sequences of project checkpoints are used to synchronize stakeholders' expectations?

34. How many sequences of project checkpoints are used to synchronize stakeholders' expectations?

  1. 2
  2. 4
  3. 3
  4. 8

Answer: C) 3

Explanation:

Three sequences of project checkpoints are used to synchronize stakeholders' expectations: Major milestone, minor milestone, and status assessments.