The chart that shows the project task against the calendar is called ____?

47. The chart that shows the project task against the calendar is called ____?

  1. Major milestone
  2. Minor milestone
  3. Gantt chart
  4. Status assessment

Answer: C) Gantt chart

Explanation:

The horizontal chart that shows the project task against the calendar is called the Gantt chart.