    Which chart represents the amount of work remaining in the project?
    
    
    
    28. Which chart represents the amount of work remaining in the project?
    
      - Burn-up chart
 
      - Burn down chart
 
    
    Answer: B) Burn down chart
    Explanation:
    Burn down chart describes the amount of work left/remaining in the project.